We have submitted an application to the DfT Structures Fund to support the replacement of the deteriorated section of Dunbar Avenue Culvert at the junction of Dunbar Avenue and Norbury Crescent.
The proposed scheme would replace the culvert deck beneath Dunbar Avenue, remove the longstanding weight restriction and restore the structure to modern highway loading standards.
Dunbar Avenue Culvert carries the local highway over a watercourse and forms an important link within the local road network, providing access for residents, local businesses, service vehicles and emergency services.
The structure has been subject to a 7.5-tonne weight restriction for more than 20 years due to deterioration of the existing culvert deck. While the structure remains safe to use under the current restriction, continued deterioration could lead to further restrictions or eventual closure if improvements are not undertaken.
The proposed scheme will replace the existing culvert deck. This will restore the structure to 40-tonne highway loading standards, providing a long-term solution and improving the resilience of the local highway network.
The proposed works would:
Traffic assessments estimate that approximately 2,200 vehicles use Dunbar Avenue each day, and the route is commonly used as an alternative local route during busy periods to help relieve congestion on nearby roads.
The culvert is located within Flood Zone 3. The replacement has been designed to maintain the existing watercourse capacity while improving the long-term resilience of the structure, helping to reduce the risk of future disruption during periods of heavy rainfall.
Subject to the necessary statutory consents, the Council will progress the detailed design before commencing construction. The works will be delivered through the Council's established highways delivery arrangements, with appropriate traffic management in place to minimise disruption to residents, businesses and road users. Further information on the construction programme will be published as the project progresses.
We have submitted an application to the DfT Structures Fund to help deliver this scheme. The funding application is currently being assessed by the Department for Transport, and a decision is expected following the assessment process. We will also provide a local contribution alongside the requested Government funding.