London Borough of Croydon

We are improving Walking and Cycling

We are investing over £3m to provide cycle and walking links to Croydon town centre and surrounding parks and green spaces.  

The Connect2 scheme is divided into ‘core network’ and ‘wider network’ sections, the locations of which are illustrated in the plan of the network (available below as a download).  

The Connect2 project is funded by Croydon Council, Transport for London, and Sustrans. The core network is fully funded. 

Addiscombe Railway Park

Works Completed So Far

The scheme has so far provided the core route between Wandle Park and Park Hill Recreation Ground including:

  • Pedestrian and cycle crossings of Park Lane, the A232 Croydon Flyover, Roman Way and Barclay Road
  • A walking route along the tram system between Wandle Park and Ampere Way Tramstops). 
  • New zebra crossings on Waddon Road and Charles Street

We have also provided the following parts of the wider network:

  • The cycle route in Phase 2 of Addiscombe Railway Park 

Park Lane Pedestrian / Cycle crossing

Proposed Works

To complete the ‘core route’ it is proposed to create:

  • New cycle routes in three of Croydon’s Parks (Wandle Park, Park Hill Recreation Ground and Lloyd Park)
  • An ‘on road’ cycle link between Park Hill and Lloyd Park using Chichester Road and Deepdene Avenue
  • A further cycle link between the New South Quarter development and Wandle Park (across the Tram System)
  • A widened footway /cycleway between New South Quarter and Waddon Marsh Tram Stop

Connected Croydon – Connect2
 

Completion of Core Route

Start on site: September 2016

Completion: March 2018

If you have any questions please contact the project manager, Tom Sweeney tel. 020 8726 6000 ext 62575 email tom.sweeney@croydon.gov.uk

Please follow us on Twitter @yourcroydon.

Help downloading files

Downloads

Help downloading files